This is usually a thirty minute - one hour meeting going over details of what you are looking for in your new pool and taking measurements of the build site
Following the on-site meeting our team will design a custom plan tailored to your choices and build-site.
Once the plan design has been completed we will begin working on pricing
Once pricing has been agree upon we will prepare and sign the contract to get started
Once the contract has been signed we will begin the permitting process and call for a dig test to locate where underground lines are located
Once permitting has been approved we will have a dig date where the excavation company will layout and dig the pool
Once excavation has been completed rebar will be installed
Once steel has been installed the electric contractor will install a copper bonding wire around the pool.
Inspector will check the bonding wire
Plumbing will be installed
Once plumbing is installed we will be ready for gunite
The tile and coping you selected will then be installed
Electric will be run to the equipment
Flatwork will be formed up and ready for inspection
Inspection will be done to approve steel and bonding wires are in place
Flat-work will be poured
Plaster will be installed and depending on material will be filled immediately or the next day
Brushing will begin to help with the curing of the plaster and chemicals will be added to balance water
Inspection will be done to make sure pool is complete and fencing has been installed
A pool school will be scheduled on how to operate and maintain your new pool
Enjoy your new pool and start making memories